Managing
Window Replacement Projects
By Frank Bartlett
Associate Director of Residence Life
University of Wisconsin - Whitewater
I don't
know how many of you have looked at changing out your window units recently,
but it certainly proved to be an interesting project for me at The University
of Southern Mississippi. With past projects I was able to specify items
and installation methods, but the window project was a little too challenging
for that.
We had
a problem in Pulley Hall, a six story, 30-year old residence hall. When
it rained, as it often does in the fall and winter months in Mississippi,
a large number of the windows in the facility leaked. Depending upon the
severity of the rains the number of rooms impacted could be 15 and up.
An attempt to remedy this situation had taken place about 5 years prior
as a contractor was hired to caulk the windows and paint the fiberglass
panel under the window unit. Clearly, the fix was short term at best in
regard to stopping the leaks as well as painting over the fiberglass panel.
As such, the Residence Life department had identified funds available
for an improvement project; we just needed to make it happen.
The windows
were not the residential sash and sill variety. The windows each had a
52" by 10 foot opening that included a paneled area underneath the window.
In addition, the panel underneath was comprised of an asbestos insulating
material that would need to be specially removed and disposed of. A reality
of the finished project would be modern tinted windows that are aesthetically
attractive, energy efficient and would meet the needs of the student of
today and beyond.
Our goal
was to implement the window project during the summer of 2000. Our challenge
was that it was already the beginning of November 1999. We had identified
the style of windows we wanted installed, we just needed the project to
be designed and coordinated. We had thought about writing the specifications
for bid ourselves, but with the asbestos abatement the project would be
best served by experts.
Contact
was made through the Physical Plant offices at The University of Southern
Mississippi. An architect was recommended that had experience with projects
involving the removal and disposal of asbestos. A project manager was
appointed within the Physical Plant department, and the Board of Trustees
gave the go ahead for the Architect to be hired. An architect from Slaughter/Allred
/McNabb P.A. was selected.
The architect
was able to take the information regarding the direction we wanted to
go with the project and compile a bid document. There were three meetings
in which we discussed the project and our needs regarding the project
(project scheduling, window requirements, etc). We were clearly in a rush
with the project as the summer was rapidly approaching. The bid process
would take a month, and the ordering of windows would take three months.
The bid
document was finalized and the project went out to bid on January 13,
2000 with bid opening to take place on February 11, 2000. The bids were
opened and compared to the specifications of the bid document. Based upon
the specifications of the bid, the contract was awarded.
We made
the project even more complicated by coordinating an asbestos removal
of the flooring with a flooring replacement to occur after the windows
were installed. Being as we were doing some asbestos abatement, it made
sense to take care of all of the building needs at that particular time.
Of course, the flooring project didn't fall under the supervision of the
architect and so it made matters a bit more challenging.
The
projected timeline for the project was:
 |
May
13th |
Residents
move out of the building by 8am in the morning. |
| |
May
13th |
The
maintenance staff would enter the building and remove/relocate items
in the rooms. Beds and mattresses would be placed in another hall
and new ones furnished at the end of the summer. The chairs and microfridges
were placed in the closets. The rest of the furniture was built in. |
| |
May
15th |
The
abatement of the floors and windows would begin. |
| |
May
20th |
The
installation of the windows would begin. |
| |
June
1st |
The
installation of the flooring would begin. |
| |
July
28th |
The
window installation process would be completed. |
| |
August
4th |
The
flooring project would be completed. |
As with
most projects, not everything went according to schedule. The clearing
of the building occurred without incident, but we were quickly reminded
about just how much "stuff" is contained in one residence hall. The abatement
started without a hitch, but took a little longer than expected. A decision
was also reached between the abatement vendor and window installer that
the asbestos panels would be removed one floor at a time. The delivery
of the windows didn't arrive early as the installers had anticipated.
When the installation began, it was at a very slow pace making us a little
nervous. When the window installation got up to full speed, they were
installing windows on a floor over a two-day period with the exception
of bathroom, hallway and stairwell windows.
The flooring
installation was delayed until the window installation was underway. The
quality of the flooring contractors made up for the shorter time period
available to them.
Suggestions:
- It is
best to go with an architect to design and oversee the project.
- Allow
enough time for the proper design, bid process and ordering. The project
should have been started in late summer by at least September to avoid
pressing the issue.
- Set
up a time schedule that is functional for both contractors and the needs
of the University.
- When
trying to coordinate different projects within the same facility and
space. Be organized, communicate and do everything possible to keep
people on task or timeline.
About the Author
Frank Bartlett
is the Associate Director for Residence Life at the University of Wisconsin
- Whitewater. Prior, Frank was the Assistant Director for Residence Life
for Maintenance and Custodial Services at the University of Southern Mississippi.
Frank made the transition to supervising maintenance functions after a
number of positions focused in residence life.